Menu

Case Study

Hiding a structural renovation in plain sight

Harris Theater

The Joan W. and Irving B. Harris Theater for Music and Dance is Millennium Park’s indoor performing arts venue. The 1,525-seat theater is mostly underground due to the restrictions to building in Grant Park. The $5 million renovation includes expansion of the lobby, installation of two high speed elevators and reconfiguration of monumental stairs.

The challenges included inserting the new circulation elements within an existing building whose precast structural elements are exposed and architecturally finished. The elevator pits were hung from an existing caisson and grade beam foundation. The concealed connections of the new precast required connecting to existing structure not originally designed for the connection.

Intense and exhaustive field evaluation of existing elements was performed to fit the new connections. Ultimately, the connections needed to once again be concealed, much more easily accomplished in new construction than renovation. The resulting solutions met all of the structural and aesthetic challenges.

Challenge

Renovations can prove challenging, even more so when the structure is architecturally expressed and completed modifications are left visible. The original design of the mostly underground theater envisioned that most patrons would enter from the adjacent underground parking garage. But the success of Millennium Park and adjacent neighborhood resulted in most attendees entering at street level. A more inviting vertical circulation and expansion of the lobby was desired. That meant new glass elevators, and reconfigured monumental stairways plying through the 82 foot-tall lobby with a below grade addition.

Solutions

The concealed connections of the new precast required connecting to existing structure not originally designed for the connection. Intense and exhaustive field evaluation of existing elements was
performed to fit the new connections. Ultimately, the connections needed to once again be concealed, much more easily accomplished in new construction than renovation.

The elevators had their own challenges not only in penetrating through all levels of the precast floors, but also below the lowest level. The building is supported on deep foundations. So the elevator pits were hung from the existing caissons and grade beams. The downstairs lobby was expanded by 30%, in the same architectural manner of exposed precast concrete structure.

Results

The resulting solutions met all of the structural and aesthetic challenges. The precast concrete is again the final finish. All the structural connections are visible, and exposed to view, available for inspection, if you can find them.

Harris Theater Case Study
Harris Theater Case Study
Harris Theater
Harris Theater Case Study Harris Theater Case Study
Harris Theater Case Study
Harris Theater Harris Theater

Let’s work together to create seamless solutions